More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – August 15, 2017

Tuesday, August 15, 2017   12:00 p.m.

Weeks Marine has worked intermittently over the last few days, as marine conditions allowed. With Hurricane Gert forecasted to pass offshore, high waves are expected today and tomorrow. Weeks Marine is closely monitoring the weather. Once work resumes, work will continue in the section of beach just north of Buxton for approximately twenty four hours of pumping and then work will proceed south from the subline towards the village of Buxton.
The second subline for a hopper dredge was laid on Friday, August 11 approximately 5,000 feet north of the original subline. The arrival of a hopper dredge has been delayed and the anticipated arrival date will be announced once the updated mobilization plan has been determined.
To view the project map, click here.
The next update will be issued when pumping of sand resumes.

 

 

[stop by our office to get your ‘soon to be collector item’ T-shirts].

We Got pumped T-shirts - Cape Hatteras Motel

Cape Hatteras Motel recently topped 11,247 fans on Facebook!

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *