Nourishment dredge paused - Cape Hatteras Motel

Buxton Beach Re-nourishment Update VIDEO For Wednesday July 5, 2017

Re-nourishment dredging is pausing, for the moment  … 

Check out the latest Buxton Beach Re-nourishment Update VIDEO for Wednesday July 5, 2017 by Jan Dawson at Cape Hatteras Motel.

Cape Hatteras Motel recently topped 10,265 fans on Facebook!

Launch Pad Buxton Beach Nourishment - Cape Hatteras Motel

Buxton Beach Re-nourishment Update VIDEO For Tuesday June 27, 2017

Strap-in  … the nourishment launch pad is almost ready!

Check out the latest Buxton Beach Re-nourishment Update VIDEO for Tuesday June 27, 2017 by Jan Dawson at Cape Hatteras Motel.

Cape Hatteras Motel recently topped 10,150 fans on Facebook!

Buxton Beach Nourishment - Cape Hatteras Motel

Buxton Beach Re-nourishment Update VIDEO For Monday June 26, 2017

Check out the latest Buxton Beach Re-nourishment Update VIDEO for Monday June 26, 2017 by Jan Dawson at Cape Hatteras Motel.

They’re pumping sand again, and … Cape Hatteras Motel recently topped 10,000 fans on Facebook.

Buxton Beach Re-nourishment - Cape Hatteras Motel

Buxton Beach Re-nourishment Update VIDEO For Thursday June 22, 2017

Check out the latest Buxton Beach Re-nourishment Update VIDEO for Thursday June 22, 2017 by Jan Dawson at Cape Hatteras Motel.

They’re finally pumping sand and … Cape Hatteras Motel just topped 10,000 fans on Facebook.

Buxton Beach Nourishment - Cape Hatteras Motel

Buxton Beach Re-nourishment Update VIDEO For Wednesday June 21, 2017

Check out the latest Buxton Beach Re-nourishment Update VIDEO for Wednesday June 21, 2017 by Jan Dawson at Cape Hatteras Motel.

More News … Cape Hatteras Motel just topped 10,000 fans on Facebook.

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – June 19, 2017

Due to rough seas, pumping for the Buxton beach nourishment project did not begin on Saturday, June 17. Weeks Marine reports pumping is now estimated to begin midweek, weather permitting.

The starting point for the project, where subline connects with the onshore pipes, is approximately 1,000 feet north of the northern boundary for the village of Buxton. Once pumping operations begin, crews will begin building a pad around the landing point of the subline. Once the pad is completed, construction will initially proceed to the north until reaching the temporary resource protection area that has been established by the National Park Service to protect nesting birds. At that point, crews will move back to the project’s initial starting point and proceed south. When the resource protection area is no longer in place, work will resume to the north. After work is completed to the northern project boundary, work will resume to the south until the project is completed.

Once construction begins, the project is expected to be completed in approximately 90 days under normal conditions.

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – June 15, 2017

At the pre-construction meeting on Wednesday, June 14, Weeks Marine announced that the pumping of sand for the Buxton beach nourishment project is now estimated to begin on Saturday, June 17, 2017.

Representatives from the company reported that resources are now in place for the start of the project. An 8,000 foot subline (30 inch steel pipe) was submerged toward the borrow area on Sunday, June 11. The dredge C. R. McCaskill was towed towards Buxton on June 13 and is currently positioned offshore of the project area.

The starting point for the project, where subline connects with the onshore pipes, is approximately 1,000 feet north of the northern boundary for the village of Buxton. Once pumping operations begin, crews will begin building a pad around the landing point of the subline. Once the pad is completed, construction will initially proceed to the north until reaching the temporary resource protection area that has been established by the National Park Service to protect nesting birds. At that point, crews will move back to the project’s initial starting point and proceed south. When the resource protection area is no longer in place, work will resume to the north. After work is completed to the northern project boundary, work will resume to the south until the project is completed.

Once construction begins, the project is expected to be completed in approximately 90 days under normal conditions.

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Re-nourishment Update VIDEO For Sunday June 11, 2017

Check out the latest Buxton Beach Re-nourishment Update VIDEO for Sunday June 11, 2017 by Jan Dawson at Cape Hatteras Motel

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – May 25, 2017

At a pre-construction meeting on Wednesday, May 24, Weeks Marine announced that the pumping of sand for the Buxton project is now estimated to begin in mid-June.

Representatives from the company reported that the subline for the project is en route and scheduled to arrive early next week. Once in Dare County, the subline will be assembled (approximately 8,000 feet of 30 inch steel pipe) and laid in place underwater. The booster pump, necessary to pump sand to the north end of the project area, will also soon be en route. The C.R. McCaskill, the cutter head dredge assigned to the project, will arrive once the subline has been placed.

The starting point for the project, where offshore pipes connect with the onshore pipes, is approximately 1,000 feet north of the northern boundary for the village of Buxton. Construction will initially proceed to the north until reaching the temporary resource protection area that has been established by the National Park Service to protect nesting birds. At that point, crews will move back to the project’s initial starting point and move south until the resource protection area is no longer in place and work will then resume to the north. After work is completed to the northern project boundary, work will resume to the south until the project is completed.

Once construction begins, the project is expected to be completed in approximately 90 days under normal conditions.

For more information, please visit MoreBeachToLove.com.

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – May 8, 2017

Weeks Marine, the contractor for the Buxton beach nourishment project, has announced the first day of pumping has been postponed from the originally projected date of May 21 to sometime within the last week of May.

The starting point for the project, where the offshore pipes connect with the onshore pipes, will be located at the oceanfront approximately 1000 feet north of the northern boundary of the village of Buxton. Weeks Marine has announced project construction will initially proceed to the north of the starting point.

The whole project is expected to be completed within 90 days under normal conditions – approximately 55 days for the project area north of the starting point and approximately 35 days for the southern portion.

For more information about beach nourishment projects taking place in Dare County in 2017, please visit MoreBeachtoLove.com