Buxton Beach Nourishment Update – July 5, 2017

Buxton Dredging Operations for Re-nourishment on Hold

With rough sea conditions forecasted later this week, Weeks Marine has announced that that the dredge C.R. McCaskill will travel to Norfolk to ensure safety. The McCaskill is expected to return next week and resume operations by Wednesday, July 12.  Travel time to Norfolk is approximately two and a half days. While there, the dredge will undergo routine maintenance.

Approximately 10% of the project has been completed thus far and the project manager representing Dare County reports that the sand being pumped from offshore is excellent quality.

Nourishment dredge paused - Cape Hatteras Motel

Buxton Beach Re-nourishment Update VIDEO For Wednesday July 5, 2017

Re-nourishment dredging is pausing, for the moment  … 

Check out the latest Buxton Beach Re-nourishment Update VIDEO for Wednesday July 5, 2017 by Jan Dawson at Cape Hatteras Motel.

Cape Hatteras Motel recently topped 10,265 fans on Facebook!

Launch Pad Buxton Beach Nourishment - Cape Hatteras Motel

Buxton Beach Re-nourishment Update VIDEO For Tuesday June 27, 2017

Strap-in  … the nourishment launch pad is almost ready!

Check out the latest Buxton Beach Re-nourishment Update VIDEO for Tuesday June 27, 2017 by Jan Dawson at Cape Hatteras Motel.

Cape Hatteras Motel recently topped 10,150 fans on Facebook!

Buxton Beach Nourishment - Cape Hatteras Motel

Buxton Beach Re-nourishment Update VIDEO For Monday June 26, 2017

Check out the latest Buxton Beach Re-nourishment Update VIDEO for Monday June 26, 2017 by Jan Dawson at Cape Hatteras Motel.

They’re pumping sand again, and … Cape Hatteras Motel recently topped 10,000 fans on Facebook.

Buxton Beach Re-nourishment - Cape Hatteras Motel

Buxton Beach Re-nourishment Update VIDEO For Thursday June 22, 2017

Check out the latest Buxton Beach Re-nourishment Update VIDEO for Thursday June 22, 2017 by Jan Dawson at Cape Hatteras Motel.

They’re finally pumping sand and … Cape Hatteras Motel just topped 10,000 fans on Facebook.

Buxton Beach Nourishment - Cape Hatteras Motel

Buxton Beach Re-nourishment Update VIDEO For Wednesday June 21, 2017

Check out the latest Buxton Beach Re-nourishment Update VIDEO for Wednesday June 21, 2017 by Jan Dawson at Cape Hatteras Motel.

More News … Cape Hatteras Motel just topped 10,000 fans on Facebook.

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – June 19, 2017

Due to rough seas, pumping for the Buxton beach nourishment project did not begin on Saturday, June 17. Weeks Marine reports pumping is now estimated to begin midweek, weather permitting.

The starting point for the project, where subline connects with the onshore pipes, is approximately 1,000 feet north of the northern boundary for the village of Buxton. Once pumping operations begin, crews will begin building a pad around the landing point of the subline. Once the pad is completed, construction will initially proceed to the north until reaching the temporary resource protection area that has been established by the National Park Service to protect nesting birds. At that point, crews will move back to the project’s initial starting point and proceed south. When the resource protection area is no longer in place, work will resume to the north. After work is completed to the northern project boundary, work will resume to the south until the project is completed.

Once construction begins, the project is expected to be completed in approximately 90 days under normal conditions.

Buxton Beach Nourishment - Cape Hatteras Motel

Buxton Beach Re-nourishment Update VIDEO For Thursday June 15, 2017

Check out the latest Buxton Beach Re-nourishment Update VIDEO for Thursday June 15, 2017 by Jan Dawson at Cape Hatteras Motel

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – June 15, 2017

At the pre-construction meeting on Wednesday, June 14, Weeks Marine announced that the pumping of sand for the Buxton beach nourishment project is now estimated to begin on Saturday, June 17, 2017.

Representatives from the company reported that resources are now in place for the start of the project. An 8,000 foot subline (30 inch steel pipe) was submerged toward the borrow area on Sunday, June 11. The dredge C. R. McCaskill was towed towards Buxton on June 13 and is currently positioned offshore of the project area.

The starting point for the project, where subline connects with the onshore pipes, is approximately 1,000 feet north of the northern boundary for the village of Buxton. Once pumping operations begin, crews will begin building a pad around the landing point of the subline. Once the pad is completed, construction will initially proceed to the north until reaching the temporary resource protection area that has been established by the National Park Service to protect nesting birds. At that point, crews will move back to the project’s initial starting point and proceed south. When the resource protection area is no longer in place, work will resume to the north. After work is completed to the northern project boundary, work will resume to the south until the project is completed.

Once construction begins, the project is expected to be completed in approximately 90 days under normal conditions.

Bridge Construction Update - Cape Hatteras Motel

Hatteras Island Bridge Update VIDEO For Wednesday June 14, 2017

Check out the latest Hatteras Island Bridge Update VIDEO for Wednesday June 14, 2017 by Jan Dawson at Cape Hatteras Motel.

Impressive work and once-in-a-lifetime views of a spectacular construction process in action on Highway NC12 … plus PROGRESS IN ACTION!

We’ve all waited patiently on the edge for decades, so it’s quite exciting to share with all of our loyal fans and patrons, both a new bridge spanning Oregon Inlet and 300′ of sand replenishment where desperately needed. Thanks to all who made these things happen.