More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – August 23, 2017

Wednesday, August 23, 2017   2:00 p.m.

Due to the upcoming marine forecast, the cutter dredge C.R. McCaskill will be leaving Buxton on Thursday, August 24 to ensure safety for the crew and equipment.  Since the dredge is likely to be offsite for at least seven to ten days, Weeks Marine has decided to utilize this downtime to have the U.S. Coast Guard’s mandatory dry dock inspection performed. The dredge will sail to Charleston, SC for a two week dry dock period and then return to Buxton to resume work.

The hopper dredge R.N. Weeks is scheduled to arrive in mid September and the current plan is to operate both dredges (the McCaskill and the R.N. Weeks) until the project is completed.

Additional updates will be provided as new information becomes available.

 

[stop by our office to get your ‘soon to be collector item’ T-shirts].

We Got pumped T-shirts - Cape Hatteras Motel

Cape Hatteras Motel recently topped 11,317 fans on Facebook!

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – August 17, 2017

Thursday, August 17, 2017  1:15 p.m.

The cutterhead dredge C.R. McCaskill resumed pumping Wednesday afternoon around 3 p.m.  Work in the section of beach just north of the subline has been completed. Weeks Marine will grade the newly nourished beach and open it to the public later this afternoon.

Also this afternoon, crews will flip the pipeline and begin working south towards the village of Buxton. It is expected to take 20 to 24 days of full pumping production to finish the south side of the project from the current landing point.

As work moves through Buxton, beach goers in the project area are advised to use caution, stay out of marked off work zones, and adhere to instructions and signs posted by construction crews on site.

As reported previously, a second subline for a hopper dredge was installed last Friday approximately 5,000 feet north of the existing subline; however, the arrival of a second dredge was delayed.  Weeks Marine estimates that the hopper dredge R.N. Weeks should arrive and be able to start pumping sand in the second week of September.

At this point, approximately one third of the project has been completed.

The project map will be updated later today, once the new construction zone is designated.

 

[stop by our office to get your ‘soon to be collector item’ T-shirts].

We Got pumped T-shirts - Cape Hatteras Motel

Cape Hatteras Motel recently topped 11,257 fans on Facebook!

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – August 15, 2017

Tuesday, August 15, 2017   12:00 p.m.

Weeks Marine has worked intermittently over the last few days, as marine conditions allowed. With Hurricane Gert forecasted to pass offshore, high waves are expected today and tomorrow. Weeks Marine is closely monitoring the weather. Once work resumes, work will continue in the section of beach just north of Buxton for approximately twenty four hours of pumping and then work will proceed south from the subline towards the village of Buxton.
The second subline for a hopper dredge was laid on Friday, August 11 approximately 5,000 feet north of the original subline. The arrival of a hopper dredge has been delayed and the anticipated arrival date will be announced once the updated mobilization plan has been determined.
To view the project map, click here.
The next update will be issued when pumping of sand resumes.

 

 

[stop by our office to get your ‘soon to be collector item’ T-shirts].

We Got pumped T-shirts - Cape Hatteras Motel

Cape Hatteras Motel recently topped 11,247 fans on Facebook!

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – August 10, 2017

Thursday, August 10, 2017    2:00 p.m.

Weeks Marine resumed pumping sand this morning around 9:30 after two days of being shut down due to weather. The current marine forecast looks favorable for pumping the next several days.

The cutterhead dredge McCaskill will work on filling a 900-foot section of beach just north of Buxton during the next five days of pumping and will then proceed south through the village of Buxton.

In the meantime, Weeks Marine will be setting up a second subline approximately 5,000 ft north of the current subline.  A second dredge – a hopper dredge – is scheduled to arrive in Buxton next week, weather permitting.  Once the second dredge arrives and passes the Army Corps’ on-site pre-dredging inspection, pumping will start from the newly placed northern subline and proceed south.

 

[stop by our office to get your ‘soon to be collector item’ T-shirts].

We Got pumped T-shirts - Cape Hatteras Motel

 

Cape Hatteras Motel recently topped 11,155 fans on Facebook!

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – August 7, 2017

August 7, 2017 3:30 pm

Coastal Science and Engineering (CSE), project manager for the Buxton Beach Nourishment Project, provided a detailed update at the Dare County Board of Commissioners’ meeting on Monday morning, August 7. CSE discussed production improvement measures that are being considered to expedite construction. They reported that Weeks Marine is hoping to bring a second dredge and will work through inspections and other requirements in an effort to bring the ‘B.E. Lindham’ hopper dredge on site in the next 10 – 15 days.

To view the PowerPoint presentation from CSE, click here.

Video of the presentation will be posted on MoreBeachtoLove.com as soon as available.

The next update will be issued as soon as work on the project resumes, or sooner if updated information becomes available

 

[stop by our office to get your ‘soon to be collector item’ T-shirts].

We Got pumped T-shirts - Cape Hatteras Motel

Cape Hatteras Motel recently topped 11,025 fans on Facebook!

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – August 4, 2017

 August 4, 2017  5 p.m.

Weeks Marine pumped sand steadily this morning and shut down operations just before 3 p.m. due to rising sea conditions.

With the dredge shut down, Weeks Marine’s beach crew plans to disconnect the pipes in front of the Cape Hatteras Motel and grade the newly nourished beach and open it to the public.  When sea conditions subside, work will proceed a short distance to the north of the current landing point to complete the section between the previous landing point and the current landing point to the full design volume.  Once that section of beach is completed, pumping will resume south.

As work resumes south through the village of Buxton, remember to use caution, stay out of marked-off work zones, and adhere to instructions and signs posted by construction crews on site.  Please keep in mind that schedules and plans are subject to change.

The next update will be issued when work resumes.

 

[stop by our office to get your ‘soon to be collector item’ T-shirts].

We Got pumped T-shirts - Cape Hatteras Motel

 

 

Cape Hatteras Motel recently topped 11,020 fans on Facebook!

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – August 2, 2017

Buxton Beach Nourishment Update … Wednesday, August 2, 2017 … Pumping Resumed

After having to shut down pumping operations on Friday morning, July 29 due to rough sea conditions, the pumping of sand resumed this afternoon just after 4:00 p.m. Construction is moving to the south and has approached the north end of Buxton.

Rough sea conditions on Friday, August 4 may lead to another delay over the weekend, but Weeks Marine estimates that if the current forecast holds, sea conditions will allow them to work for approximately four days over the coming week.

At this point, approximately 22% of the project has been completed. Updates will be provided as additional information is available.

 

 

[stop by our office to get your ‘soon to be collector item’ T-shirts].

 

We Got pumped T-shirts - Cape Hatteras Motel

Cape Hatteras Motel recently topped 11,015 fans on Facebook!

 

 

 

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – July 21, 2017

Weeks Marine has announced the change of pumping directions over the course of the next week.  An anticipated weather delay may cease pumping operations this weekend for the Buxton project.  The dredge C.R. McCaskill plans to remain on site during this weather delay.  When pumping is forced to shut down due to rough sea conditions, the beach crews will detach the current pipeline and transit the pipes to the south of the subline.  The newly nourished beach is expected to open to public after Weeks Marine moves the active construction zone to the south.  When pumping operations resume sometime next week, construction will proceed south from the subline towards the village of Buxton.

For more information about current beach nourishment projects in Dare County, projects maps and frequently asked questions, please visit MoreBeachtoLove.com

Buxton Beach Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – July 17, 2017

The dredge CR McCaskill has returned to Buxton and work has resumed, moving to the north. Click here to view the project map.

 

Approximately 10% of the project has been completed so far. Updated information will be posted as soon as information is available.

 

For details about all beach nourishment projects occurring in Dare County, please visit MoreBeachtoLove.com.

 

More Beach To Love Re-Nourishment - Cape Hatteras Motel

More Beach To Love Re-Nourishment - Cape Hatteras Motel

Buxton Beach Nourishment Update – July 12, 2017

Buxton Dredging Operations for Re-nourishment back in action.

 

Weather permitting, the dredge CR McCaskill will return to Buxton on Saturday, July 15 and resume pumping sand on Sunday,  July 16. Work will move to the north.  Click here to view the project map. Approximately 10% of the project has been completed so far. Any schedule updates will be posted on MoreBeachtoLove.com as soon as information is available.